Answers to PMP Practice Questions [Project Integration Management]

Here are the answers to the PMP® Practice Questions on Project Integration Management, which I have posted earlier. I have explained why the choice is correct. I have also given references to PMBOK® Guide, Sixth Edition, wherever it is relevant.

If you are yet to see the practice questions, please check out the questions here: PMP® Practice Questions [Project Integration Management].

Answers to PMP Practice Questions (Project Integration Management)

Answers to PMP Practice Questions (Project Integration Management)

1. Correct answer: Choice D.

Change Requests can be an input to only one process, which is Perform Integrated Change Control. Change Request, wherever generated in the project, has to be an input to this process. Please remember that only Perform Integrated Change Control process can review and approve/ reject the change requests.

2. Correct answer: Choice C.

Project Charter is the document that authorizes the existence of a project and empowers the project manager to obtain resources for the project. So, the project manager should show the project charter, which should convince the functional manager.

3. Correct answer: Choice C.

Describing the product, service or result boundaries, and acceptance criteria is the benefit of Define Scope Process. The remaining are all the benefits of Develop Project Charter process.
Ref: PMBOK Guide, Sixth Edition, Page 75 & 150

4. Correct answer: Choice B.

Projects are initiated by an entity external to the project such as a sponsor, program or project management office (PMO), or a portfolio governing body chairperson or authorized representative.
Ref: PMBOK Guide, Sixth Edition, Page 77

5. Correct answer: Choice B.

The business case describes the necessary information from a business standpoint to determine whether the expected outcomes of the project justify the required investment.
Ref: PMBOK Guide, Sixth Edition, Page 77

6. Correct answer: Choice A.

Acceptance criteria is included as part of Project Scope Statement, while the other three are typically seen in Project Charter.
Ref: PMBOK Guide, Sixth Edition, Page 155

7. Correct answer: Choice D.

Formal authorization of a project happens at the time of project charter, not at the kick-off meeting.
Ref: PMBOK Guide, Sixth Edition, Page 86

8. Correct answer: Choice C.

While you might be carrying out all the other choices with regards to change requests, the most important role of project manager is to work towards preventing unnecessary changes in the project.

9. Correct answer: Choice B.

From the question, you can understand that the Project Charter has already been developed. Next step is to develop the project management plan.

10. Correct answer: Choice D.

As per the PMI Code of Ethics and Professional Conduct, you should bring violations of the code to the attention of senior management at the company and possibly PMI. However, you should get the facts together and gather evidence before taking either of those steps.

Conclusion

If you don’t agree with any of the answers above, feel free to post your views here. Let us discuss and come to a conclusion. If you need any clarification or further explanation on any of the concepts discussed above, please leave your comments below. I will try to address them.

Certified Project Management Professional (PMP)®
Certified Risk Management Professional (PMI-RMP)®
An enthusiastic project management practitioner and trainer.

Latest posts by Manickavel Arumugam (see all)

Most Shared Posts

Comments

  1. TG Prakash says September 15, 2020 at 5:38 pm

Questions 2,3 & 6 were wrong could able to gone through your explanation and understand the essence. Thanks
Prakash

Answer of 2nd question should be A –> As it is mentioned in Question, you have to negotiate with functional manager. So i think A represents the best Answer, If I will have to show the project charter, than what’s the point of negotiation. Its just like giving order. This is my perception. Please correct me sir. Thanks

Having a project charter does not mean that we can order functional managers? We still have to negotiate with the FMs to get the right resources at the right time in the right quantities.

I’m Vishwa, your current batch student sir. I got 8 answers correct.
Ques 2 nad 6 went wrong. I went through the explanation and understood. Thanks for sharing sir

Wonderful Vishwa! That’s an excellent score.

Hi, Thanks for sharing free questions and answers on Project Integration management. It’s highly beneficial for all who are preparing for PMP examination.Thanks again

You are welcome

Leave a Reply Cancel reply

PMP Exam Prep Live Online Training

10 Questions Quiz

You may also like

How to remember ITTOs of Project Resource Management?

This is the sixth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project resource management. What is Project Resource Management? […]

How to remember ITTOs of Project Quality Management?

This is the fifth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project quality management. What is Project Quality Management? […]

How to remember ITTOs of Project Cost Management?

This is the fourth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project cost management. What is Project Cost Management? […]

How to remember ITTOs of Project Communications Management?

How to remember ITTOs of Project Communications Management? This is the seventh article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on […]

How to remember ITTOs of Project Schedule Management?

This is the third article in the series “How to remember ITTOs”. You can refer to my earlier articles on this series here: How to remember ITTOs of Project Integration management? and How to remember ITTOs of Project Scope Management? ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this […]

PMI ® , PMP ® , and PMBOK ® Guide are trademarks of Project Management Institute, Inc.